What are my funds going towards?

You can find a breakdown of our plans here.

What has happened with the funds I have given?

Multiple projects have been started and are underway! Down below are some of the projects that the Override Bond have already helped us in improving our district. And here are the plans we have going on over the summer!

Middle School

  • Gym Floor Replacement 

    • Start Date: May 27, 2025

    • Duration: 4–6 weeks

    • Scope: Complete replacement of the gym floor with new materials.

  • Paving of Parking Lots and Play Areas

    • Start Date: June 11, 2025

    • Completion Date: July 17, 2025

    • Scope:

      • Demolition of existing concrete

      • Pulverizing and grading of main and back areas

      • Addition of ADA stalls, sidewalks, and curbing

  • Locker Room Renovation – 

    • Start Date: June 5, 2025

    • Completion Date: End of August 2025

    • Scope:

      • Demolition of current locker rooms

      • Installation of new lockers, stalls, fixtures, tile, ceilings, and lighting

      • All work will be fully ADA compliant

High School / Primary School / District Office

  • Seal Coating and Restriping of Parking Lots 

    • Start Date: June 2–3, 2025 (coating); June 3–4, 2025 (restriping)

    • Scope:

      • Spray-on seal coating for lots paved in July 2024

      • Restriping of parking stalls, fire lanes, ADA markings, and signage

High School

  • Turf Project (Outside "Old" Field) 

    • Mobilization Start: May 15, 2025

    • Scope:

      • Demolition of existing field

      • Ground preparation and drainage work

      • Installation of new turf field

    • Estimated Completion: September 2025

Bus Barn

  • Paving and Striping 

    • Start Date: June 2, 2025

    • Completion Date: June 17, 2025

    • Scope:

      • Pulverizing and grading of bus barn area

      • Paving and striping of stalls

Elementary School

  • Turf Project (Playground Turf Installation) 

    • Start Date: May 27, 2025

    • Completion Date: August 1, 2025

    • Scope:

      • Ground and drainage work

      • Installation of playground turf over existing playground

Primary School

  • Turf Project (Playground Turf Installation)

    • Start Date: May 27, 2025

    • Completion Date: August 1, 2025

    • Scope:

      • Ground and drainage work

      • Installation of playground turf over existing play areas

Pending Projects 

  • Auditorium Lighting and Sound Project- Discussion in June Board meeting

  • Bulletproof Laminate Installations- May 28, 2025

  • Dome Front Parking Lot Redesign and Drainage Improvements